Method 2

Use this method in the Order Point Report (ROP) to set the order point to a specific percentage above or below the current order point.  You may want to use this method to fine-tune sensitive items.

For example:

You can use Method 2 with Method 1. If you combine methods, the system uses the methods in numerical order.  For each item, if the first method applies, the system ignores the second method. If the first method does not apply, the system uses the second method.

For example:  You use Methods 1 and 2. For Method 1, you want to set the order point to 1 for each item whose cost is $175 or higher.  For each item, the system uses Method 1 first.