Modifying the Start or End Dates of a Future Promotion

Use the procedure below to modify the start and/or end date of all items on a promotion.

Note:  for an alternate method of making global changes to promotions, see step 5 in the topic "Modifying Promotions."

  1. From the Eagle Browser, click Reports Menu, Inventory Reports, Modify Promotions Report (RPD).  The Modify Promotional Data Report window displays.  
  2. On the page, select 2 to change dates of an existing promotion.
  3. From the Print Setup page, make changes if needed.  For a definition of each field, click here.
  4. Click (in the left pane of the window).  In the Options field, select option F.   
  For a definition of each option, click here.
  1. Click (in the left pane of the window).  A page of fields displays.  
  1. Click Run.
  2. Make sure you activate the promotion on the appropriate day by running RUP with Option F.  You may choose to run RUP in an end-of-day queue.