PO Worksheet: Change Cost across Multiple POs
When you write an order in Purchase Order Worksheet (POW) that contains
stores that are sourced as direct ship or pass thru orders, the system
creates a separate order for each store when POW is finalized. If
you discover any items on the order have an incorrect cost, you
can update all instances of that cost across multiple POs. The reason
you can do this is that all of the purchase orders have the same alternate
purchase order number. This process requires that you have option 9618
"WinMPO - Apply cost change to all instances of the item?" set
to Yes or P.
- From the Eagle Browser, type MPO in the Launch
bar, and press Enter to display the Purchasing and Receiving window.
- Display one of the purchase orders that contain
the item(s) for which you want to change the cost, and then click
P.O. Post (shift-F11).
- To change the cost of an item on this order,
double click the row of the item you want to change, or type the item
number in the “Item (SKU)” field and press Enter. Once the item is
displayed in the lower portion of the screen, click in the Cost field
and enter the new cost in either stocking units or purchasing units,
and blank out the one you didn't change and press Enter.

- If you have option 9618 set to "P,"
a message asks if you want to apply this cost across all instances
of this item. Click Yes to apply the change across all instances,
or click No to apply the cost change to only this purchase order.
If you have this option set to "Y," you will not receive
any prompt, and the change is applied to all instances of the item
across all cousin purchase orders.

- When you receive the following message, click
OK, then click Refresh to view the effect of the cost change(s) you
made.

The system updates all orders that have the
same item and the same alternate purchase order number.
- Repeat steps 3 through 5 to change the cost
of other items on the PO.