Finalizing Receipts

After reviewing receipts, you must finalize them by running the Receiving Report with the appropriate options, as described below.

  1. Display the Receiving Report window.

  2. Fill in the desired options on the different pages of the report.  On the page, in the Update Options field:

  1. Use the table below to determine how to fill in the Update Prices field.

Enter this at Update Prices

If you...

Comments

CGMR

Changed any costs or prices on the items you received

If you don't use the price matrix, don't use option M. If you use your own variable pricing scheme, don't use option G. It will change your desired gross profit percent.

blank

Did not change any costs or prices on the items you received

 

D

Do not want to update replacement cost with landed cost

The Use Landed Cost in Receiving field in Options Configuration (or Function MPC) must be Y for this option to work.

P

Want to update the retail price on the PO based on the landed cost

To use this option, both of the following must be true:

  • The Use Landed Cost in Receiving field in Options Configuration (or Function MPC) must be Y for this option to work.

  • The Update Options field on this report does not include D.

  1. Click Run to run the report.

Whether or not items not received remain on the PO as backorders depends on: